December Update:
The redevelopment project commenced on Tuesday 4th Dec and the following works are well underway:
• Completion of demolition to external areas of House A
• Remaining concrete to rear of House E
• Temporary fencing installed to rear of House E
• Temporary fire exit path around House H & D completed
• Installation of Fire hydrant to House B
• Demolition and isolation of Library & Kitchenette to House A
• Removal of trees and stumps from site
• All rubbish removed and /or secured
• Earthworks started to new extension – House F
• Temporary fencing to external boundaries to be secured
• Installation of temporary signage to entrances
Building works will cease on site over the Christmas break from Friday 21st December – Monday 7th January 2019.
See the progress:
More Copperhouse Court Redevelopment Updates
Kindred Living
25 Newton Street
Whyalla SA 5600